Following operations were carried out in the plant in Port of Arzew:
§ .A trench with 330 m length, 5 m width, and 5 m depth was excavated by dipper dredger having powerful hydraulic grab on the seabed containing mostly pressure-resistant sandstones with average uniaxial compressive strength values around 420 kg/cm².
§ Bedding and leveling works within the trench were performed.
§ .A special pipe with outer diameter of 330 cm was laid into the trench.
§ .After connecting water intake head to the outlet of the installed pipe, top of the trench was backfilled by filling materials, leveled and thus, the project was completed successfully.
Floating crane Haşmetli and hired dipper dredger Andre-B were used in the operations.
|